School Construction Project


Southgate Elementary Building Demolition

Project Review

Budget $332,576
Architect KMB Design Groups
Contractor Northwest Abatement Company

Construction Updates

  • September 2015
  • July 2015
  • June 2015
Building demolition is now complete and the site is cleared except for three buildings that are being used for the
Early Learning Program. The cleared portion of the site will be seeded later this month.
Hazardous abatement for 10 buildings being demolished at Southgate has begun and should be completed in early July. The building and site demolition will occur after abatement is done and should be complete in late July. By early August, the site is scheduled to be cleared and hydro seeded. Remaining buildings will be renovated for the district’s early learning program.
Several buildings originally constructed in the 1950’s will be demolished this summer on the school campus but the newer covered play area, administration, classroom and gym/cafeteria buildings will remain and be renovated to house the consolidation of early childhood education programs from 10 elementary schools across the district.