School Construction Project


Lakeview Hope Academy

Project Review

Size 16,127 SF - 2 Story Remodel & Addtions
Budget $4.8 Million
Architect BCRA
Contractor Neeley Contruction

Construction Updates

  • June 2016
  • May 2016
  • April 2016
  • March 2016
  • February 2016
  • January 2016
  • December 2015
  • November 2015
  • October 2015
  • September 2015
  • July 2015
  • June 2015
The nine-classroom addition is essentially complete. Final systems balancing and minor adjustments are underway. Staff and students will move into the new addition in August 2016.

A view of the new Lakeview Hope Academy Addition

Finishing touches are being applied to the classroom addition. The classroom addition is on schedule for completion.

The playground area is complete at Lakeview Hope Academy’s classroom addition.

A view of the stairs in Lakeview Hope Academy’s new classroom addition.

 

The exterior of the classroom addition is ready for painting. Furniture has been delivered and interior finishes are lmost done. The new electronic reader board is installed and landscaping is underway. The classroom addition is on schedule for completion.

An outside view of Lakeview Hope Academy's classroom addition.

A view of the first floor corridor in Lakeview Hope Academy's new addition.

A typical classroom in Lakeview Hope Academy's new classroom addition.
 

 

Exterior siding is nearing completion. Curbs for the outdoor playground area are poured and play equipment will be installed in early April. Interior painting is done and flooring is being installed now. Cabinetry will be installed this month. The classroom addition is on schedule for completion.

A typical classroom in Lakeview Hope Academy’s classroom addition.

A view of the second floor cooridor in Lakeview Hope Academy’s classroom addition.

The site of the playground area at Lakeview
Hope Academy’s classroom addition.
The exterior wall finishes should be complete by mid-February. Interior painting is at the halfway point and classrooms are being prepared for flooring and cabinets. A new reader board will be installed next month. The addition is scheduled to be ready for new furniture in late March. Students are anticipated to move into the new addition in April 2016.


Work continues on the second floor interior corridor of the classroom addition at Lakeview Hope Academy


Exterior brick work continues on Lakeview Hope Academy's classroom Addition

 

The brick veneer installation at the addition is progressing and will be completed this month. Cement board siding
begins now. Most of the window frames are in and glass will be installed soon. The interior sheetrock on the first floor is nearly complete and the second floor is about 50 percent done. The taping of the sheetrock will begin soon. The outdoor chiller unit has been set on a concrete pad so enclosure walls and a cover can be constructed around it.

Brick veneer work continues at Lakeview Hope Academy

 

The roof of the addition is installed and the exterior weather barrier is nearly complete so the interior of the addition can continue to dry. Temporary heating will be in place soon so sheetrock installation can begin in classrooms and corridors. Brick veneer installation has begun and will continue through December to be followed by cement board siding. Wall insulation as well as mechanical and electrical rough-ins are coming along. Students are anticipated to move into the new addition in April 2016.


The roof is installed and the addition is enclosed at Lakeview Hope Academy.

The second floor exterior wall framing is up and the roof sheathing is nearly complete. By mid-November the roof should be weather tight so the addition can begin to dry out and interior wall framing can be completed. Mechanical and electrical rough-in work continues.

Construction of the classroom addition continues at Lakeview Hope Academy.

The second floor exterior wall framing is complete at Lakeview Hope Academy

 

The first floor wall framing for the new addition is nearly complete and the second floor concrete slab has been poured.
Wall framing for the second floor has begun with roof framing scheduled to be finished in mid-October. Mechanical and
electrical rough-ins have also begun.

 

Construction of the classroom addition continues at Lakeview Hope Academy.

 

 

The new covered play structure is complete. The foundation for the new classroom addition is now complete and wall framing is well under way. The school and grounds will remain separated from the construction work until the project is complete in the spring of 2016.

Lakeview Construction
New covered play structure at Lakeview Hope Academy.

Lakeview Construction
Construction of the classroom addition continues at Lakeview Hope Academy.

Phase 1 work began on June 9 with demolition of the playground area for construction of the new covered play shed. Footings for the covered play shed are poured and steel erection has started. The covered play area is on schedule to be complete in late August. Three additional portable classrooms have been brought in and set in place. Work continues to connect the building sections and install the stairs and access ramps to the portables. Demolition for the new building addition has begun and will continue into early July. The mechanical and electrical systems in the existing school are being prepared for expansion into the new addition.


Demolition for the new building at Lakeview Hope Academy.


Steel beams being placed for the new play shed at Lakeview Hope academy

 

Groundbreaking nears for the construction and renovation project at Lakeview Hope Academy that will add nine classrooms, two restrooms and a detached covered play area. The project will be completed in two phases.

Phase 1 consists of the partial demolition of existing classrooms necessary to accommodate the new addition; preparation of existing mechanical and electrical systems in the building for the new addition; and construction of the new covered play area. Phase 1 begins as soon as school lets out on June 9 and is scheduled to be complete in late
August 2015.

Phase 2 is the completion of the new addition which will begin in late August and continue until mid-March 2016. Until construction is complete, the school will utilize some existing classrooms in the nearby Boys and Girls Club and early learning facilities as well as additional temporary portable classrooms. The portables will be removed over the summer of 2016 after the 2015-16 school year. Funding for the project comes from savings achieved from the 2010 voter-approved, school construction project for Hudtloff Middle School, which was completed in September 2013. The additional classrooms are needed due to significant student growth in the northeastern area of Lakewood and the addition of full day kindergarten in several elementary schools across the district.